Key points in 30 seconds
- Two dossiers: a preliminary dossier before fabrication, and a final dossier after fabrication and testing.
- No fabrication until ARH has approved the preliminary dossier.
- Applicable regulations: mainly Executive Decree 21-261, as well as Executive Decree 21-257.
- Who submits? Always the project owner (Maître de l'Ouvrage).
- Most common reasons for rejection: incorrect calculations, incomplete welding dossier, tests performed below regulatory requirements.
Which equipment is concerned?
The ARH dossier applies to pressure equipment (ESP) and regulated electrical equipment intended for hydrocarbon facilities in Algeria. The main regulation governing this equipment is Executive Decree 21-261. Executive Decree 21-257 also applies.
You are concerned if you are a project owner (operator), an EPC contractor or a manufacturer, based in Algeria or abroad, and the equipment is intended for an Algerian facility.
The 2 stages: preliminary dossier, then final dossier
1. The preliminary dossier: before any fabrication
As required by Decree 21-261, the preliminary dossier must be prepared, submitted and approved by ARH before fabrication starts on the pressure equipment or regulated electrical equipment.
Only once this dossier is approved can the manufacturer start fabrication. Starting earlier means taking the risk of having to rework all or part of the equipment if ARH requests changes.
2. The final dossier: after fabrication and testing
Once fabrication is complete and the regulatory tests have been performed, a final dossier must be prepared and submitted to ARH for approval on site.
What does the dossier contain?
The exact content depends on the equipment, but it generally includes:
| Document | Purpose |
|---|---|
| Consular documents | Legalized administrative documents, required for the dossier to be admissible. |
| Drawings | Define the design of the equipment. |
| Calculation notes | Justify the sizing, in line with ARH requirements. |
| ITP (Inspection and Test Plan) | Lists the inspections and tests planned at each stage of fabrication. |
| Welding dossier | Documents the welding procedures used (for welded equipment). |
| Other documents | Depending on the type of equipment and ARH requests. |
Pressure or electrical equipment: what changes?
The two-stage process is the same. However, the technical content of the dossier differs on three points:
- Calculations: the calculation notes are not the same for pressure equipment and for electrical equipment.
- Standards: different standards apply.
- Regulatory tests: the tests to be performed are different.
Who submits the dossier?
The dossier is always submitted by the project owner (Maître de l'Ouvrage), even when the documents are prepared by the manufacturer, the EPC contractor or a consultancy.
The 3 mistakes that get a dossier rejected
- Incorrect calculations, or calculations that do not meet ARH requirements. A calculation note that is technically sound but does not follow ARH requirements will still be rejected.
- A missing welding dossier, or one full of errors. It is one of the most closely checked documents.
- Regulatory tests performed below requirements. An insufficient test may have to be repeated, which delays commissioning.
Have your dossier checked before submission
A rejected dossier means lost time on your schedule. RD Energy & Industry reviews your preliminary and final dossiers (calculations, welding dossier, ITP, tests) before they are submitted to ARH, and tells you what needs to be corrected. We work in English and French with owners, EPC contractors and manufacturers in Algeria and abroad.
Frequently asked questions
Can fabrication start before the preliminary dossier is approved?
No. Decree 21-261 requires the preliminary dossier to be approved by ARH before fabrication begins.
Can the manufacturer submit the dossier itself?
No. The dossier is always submitted by the project owner. The manufacturer provides the technical documents.
When should the final dossier be prepared?
After fabrication and the regulatory tests. It is then submitted for ARH approval on site.